Applied Digital Secures $5.4bn Hyperscaler Lease, Lifting Contracted Revenue Above $41bn

Applied Digital Secures $5.4bn Hyperscaler Lease, Lifting Contracted Revenue Above $41bn

Applied Digital has signed an 18-year data center lease worth approximately $5.4 billion with an investment-grade hyperscaler, strengthening its position in the rapidly expanding market for AI computing infrastructure and bringing its total contracted base-term lease revenue above $41 billion.

The agreement covers 150 megawatts (MW) of critical IT capacity, with delivery expected to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals. Applied Digital did not disclose the identity of the tenant.

The transaction reveals the growing willingness of major technology companies to secure long-term data center capacity as demand for computing power expands alongside artificial intelligence adoption. Hyperscalers are committing billions of dollars to infrastructure capable of supporting increasingly demanding AI workloads, creating opportunities for specialist data center developers that can secure power, financing and suitable sites.

For Applied Digital, the latest agreement provides greater visibility into future revenue while strengthening the contractual foundation for its expansion. The company said the lease could be extended to a total of 33 years through renewal options, potentially increasing its value to approximately $12.7 billion if all extensions are exercised.

The company also disclosed that the new agreement carries improved commercial terms compared with its previous leases, including higher pricing. This is seen as an indication that the market value of specialized data center capacity is rising as competition for power availability and infrastructure suitable for AI computing intensifies.

The agreement follows a separate 15-year lease signed in June covering 210 MW at the company’s Delta Forge 2 site. That transaction was valued at approximately $5.2 billion, bringing the combined value of the two announced agreements to $10.6 billion in base-term contracted revenue.

Applied Digital said its total contracted base-term lease revenue now exceeds $41 billion. Including potential renewals, the figure rises to approximately $100 billion.

About 75% of the company’s contracted base-term lease revenue is tied to investment-grade customers, a measure that provides some indication of the credit quality of its tenant base.

This customer profile is important because data center development requires substantial upfront capital expenditure, often years before facilities begin generating revenue. Securing long-term agreements with financially strong tenants can improve lenders’ confidence, support project financing and reduce uncertainty around future cash flows.

The 18-year commitment also gives Applied Digital a lengthy revenue horizon, although the economics of the agreement are largely tied to construction costs, financing expenses, operating expenditure and the company’s ability to deliver the contracted capacity.

The potential $12.7 billion value over 33 years should also be distinguished from guaranteed revenue. The additional amount depends on the tenant exercising its renewal options, meaning the base-term commitment remains the more immediate measure of the contract’s financial value.

The latest transaction also gives Applied Digital an opportunity to negotiate better economics as demand for specialized AI infrastructure grows. Higher lease pricing could improve the revenue generated per megawatt of installed capacity, although the eventual impact on profitability will depend on the cost of developing and operating the facilities.

Macquarie Partnership Provides Financing Foundation

Financing the expansion remains one of the company’s most important challenges.

Applied Digital CFO Saidal Mohmand said the company plans to fund the development through its established financing structure, beginning with its $5 billion equity partnership with Macquarie Asset Management, followed by project-level financing.

The arrangement is significant because developing large-scale AI data centers requires substantial investment in land, power infrastructure, cooling systems, electrical equipment and specialized facilities before rental income begins.

Project financing could allow Applied Digital to raise capital against individual developments and their contracted cash flows rather than relying entirely on its corporate balance sheet. The Macquarie partnership also provides an equity funding framework intended to support the company’s infrastructure expansion.

However, the structure does not eliminate execution or financing risks. The company must still secure the necessary power supply, obtain regulatory approvals, complete construction and manage capital requirements before the facilities become operational.

The expected first-half 2028 delivery date illustrates the long lead times involved in converting hyperscaler commitments into revenue-generating infrastructure. Delays in electricity connections, equipment procurement, or regulatory approvals could affect construction schedules and the timing of lease payments.

More broadly, Applied Digital’s expansion illustrates how the AI investment cycle is creating a new class of infrastructure businesses whose commercial prospects depend on securing long-term contracts with major technology companies.

The market opportunity extends beyond owning data center buildings. Access to reliable electricity, high-density computing environments, cooling capacity and financing increasingly determines which developers can attract hyperscalers.

Yet the growing volume of contracted revenue does not automatically translate into equivalent cash generation or shareholder returns. Investors will need to assess how much capital Applied Digital must deploy to fulfil its commitments, the cost of financing that investment and the margins available once the facilities become operational.

Analysts say the $5.4 billion agreement represents more than another long-term lease. It strengthens Applied Digital’s contracted revenue base, demonstrates its ability to secure higher-priced capacity, and gives it another major customer commitment to support its infrastructure financing.